Hi, thanks for the information. Changing the comment column to the last comment is great!
I was using the outline as a task tracker, nesting tasks under categories, but they show on the gantt view of my programme. Can the dates be removed?
I have today been trialling managing tasks in Issues (attachments), I can group by category and use statuses, as well as showing in reports. This seemed to work alongside issues/rfis/change requests/decisions, all separated by type. (Any negatives to this?)
Lastly, I have my procurement schedule in the outline, is there a way to link a procurement date to show a gantt task install date- like a look up field, or would this be done by linking them as a predecessor?